Utilization of Management Tool In Monitoring of a Metro Project Considering Live Details : A Review

Authors

  • Vaibhav Mishra P. G. Scholar, Department of Civil Engineering, M.I.T. Bhopal, Bhilai, Madhya Pradesh, India Author
  • Afzal Khan Assistant Professor, Department of Civil Engineering, M.I.T. Bhopal, Bhilai, Madhya Pradesh, India Author

DOI:

https://doi.org/10.32628/IJSRCE

Keywords:

Primavera P6 Web, Bhopal Metro, Planning, Scheduling, Monitoring And Tracking

Abstract

Masterminding and Scheduling are the basic in the tremendous establishment project like road and augmentation improvement, Metro rail projects as these are proposed for public government help. These exercises are have different accomplices and huge proportion of money, resources are contributed. Less than ideal orchestrating and booking prompts loss of resources, extension in project cost and awful deferments. However, on account of the PC and programming headway, it now possible to plan these errands using programming takes after Primavera P6 and Microsoft office project. 
In this paper we are presenting review of literatures related to scheduling and monitoring of project using management tool.
              

Downloads

Download data is not yet available.

References

T.SIVA NAGARAJU and SRI LAKSHMANA KUMAR, [SCHEDULE AND RESOURCES OPTIMIZATION USING PRIMAVERA IN METRO RAIL PROJECT], International Journal of Mechanical And Production Engineering, ISSN: 2320-2092, Volume- 4, Issue-7, Jul.-2016.

Mohammad Afzal S. Siddiqui and Abhijit N. Bhirud, [EPS, OBS, Project Activities for Pune Metro Phase-1 in Primavera P6], Journal of Advances and Scholarly Researches in Allied Education, Vol. XV, Issue No. 2, (Special Issue) April-2018, ISSN 2230-7540.

R.Santhosh Kumar and Anoop James Antony, [Experimental Investigation on Preplanning of Road Construction by Using Primavera], International Journal of Innovative Research in Science, Engineering and Technology, Vol. 7, Issue 5, May 2018.

Abdul Aziz and Sanjeet Kumar, [Financial and Work Management Analysis for Residential Construction: a Case Study], International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-7, Issue-6C2, April 2019.

AKASH RAJKUMAR WADHWA and DATTATRAY SANTRAM SHINDE, [PROJECT MANAGEMENT USING PRIMAVERA P68.2], INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT], ISSN: 2394-3696, VOLUME 3, ISSUE 11, Nov.-2016.

Ajesh Pilaniya and Ashwin A. Mahajan, [A Review of Planning & Scheduling of a Pune Metro Rail Project using Primavera P6 Web], IJSRD - International Journal for Scientific Research & Development| Vol. 6, Issue 09, 2018 | ISSN: 2321-0613.

Alberto Cerezo-Narváez, Andrés Pastor-Fernández, Manuel Otero-Mateo and Pablo Ballesteros-Pérez, [Integration of Cost andWork Breakdown Structures in the Management of Construction Projects], Appl. Sci. 2020, 10, 1386; doi:10.3390/app10041386.

Kottamasu L. N. Panakala Rao and K. Shyam Chamberlin, [Resources Optimization in Construction of a Residential Apartment by using Primavera: a Case Study], International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-7, Issue-6C2, April 2019.

Chiranjeevi D S, Dr. G. Narayana and Rajeeva S J, [ANALYSIS ON COST, SCHEDULE AND TRACKING OF RESIDENTIAL PROJECT BY EARN VALUE MANAGEMENT METHOD USING PRIMAVERA P6], August 2017 | IJIRT | Volume 4 Issue 3 | ISSN: 2349-6002.

Downloads

Published

30-09-2021

Issue

Section

Research Articles

How to Cite

Vaibhav Mishra, & Afzal Khan. (2021). Utilization of Management Tool In Monitoring of a Metro Project Considering Live Details : A Review . International Journal of Scientific Research in Civil Engineering, 5(5), 77-83. https://doi.org/10.32628/IJSRCE

Most read articles by the same author(s)

Similar Articles

1-10 of 190

You may also start an advanced similarity search for this article.