Monitoring & Scheduling of A Metro Project (Bhopal) Work Using Project Management Tool Primavera P6
DOI:
https://doi.org/10.32628/IJSRCEKeywords:
Primavera P6 Web, Bhopal Metro, Planning, Scheduling, Monitoring And TrackingAbstract
Arranging and Scheduling are the fundamental in the enormous foundation project like street and extension development, Metro rail projects as these are proposed for public government assistance. These activities are have various partners and enormous measure of cash, assets are contributed. Ill-advised arranging and booking prompts loss of assets, expansion in project cost and terrible postponements. Yet, because of the PC and programming advancement, it now conceivable to design these tasks utilizing programming resembles Primavera P6 and Microsoft office project.
This paper manages show of metro rail project in Bhopal contrasting the two distinct stages in measure as Phase I - Subhash Nagar Phatak to Sargam Talkis and Phase II – Sargam Talkis to Saket Nagar. The task outlined expressed the benefit and added advantages of Web based primavera P6 for arranging and booking of Bhopal Metro Rail Project outlining the issues and inconveniences looked in the time span of development and accessibility of assets.
Downloads
References
T.SIVA NAGARAJU and SRI LAKSHMANA KUMAR, [SCHEDULE AND RESOURCES OPTIMIZATION USING PRIMAVERA IN METRO RAIL PROJECT], International Journal of Mechanical And Production Engineering, ISSN: 2320-2092, Volume- 4, Issue-7, Jul.-2016.
Mohammad Afzal S. Siddiqui and Abhijit N. Bhirud, [EPS, OBS, Project Activities for Pune Metro Phase-1 in Primavera P6], Journal of Advances and Scholarly Researches in Allied Education, Vol. XV, Issue No. 2, (Special Issue) April-2018, ISSN 2230-7540.
R.Santhosh Kumar and Anoop James Antony, [Experimental Investigation on Preplanning of Road Construction by Using Primavera], International Journal of Innovative Research in Science, Engineering and Technology, Vol. 7, Issue 5, May 2018.
Abdul Aziz and Sanjeet Kumar, [Financial and Work Management Analysis for Residential Construction: a Case Study], International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-7, Issue-6C2, April 2019.
AKASH RAJKUMAR WADHWA and DATTATRAY SANTRAM SHINDE, [PROJECT MANAGEMENT USING PRIMAVERA P68.2], INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT], ISSN: 2394-3696, VOLUME 3, ISSUE 11, Nov.-2016.
Ajesh Pilaniya and Ashwin A. Mahajan, [A Review of Planning & Scheduling of a Pune Metro Rail Project using Primavera P6 Web], IJSRD - International Journal for Scientific Research & Development| Vol. 6, Issue 09, 2018 | ISSN: 2321-0613.
Alberto Cerezo-Narváez, Andrés Pastor-Fernández, Manuel Otero-Mateo and Pablo Ballesteros-Pérez, [Integration of Cost andWork Breakdown Structures in the Management of Construction Projects], Appl. Sci. 2020, 10, 1386; doi:10.3390/app10041386.
Kottamasu L. N. Panakala Rao and K. Shyam Chamberlin, [Resources Optimization in Construction of a Residential Apartment by using Primavera: a Case Study], International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-7, Issue-6C2, April 2019.
Chiranjeevi D S, Dr. G. Narayana and Rajeeva S J, [ANALYSIS ON COST, SCHEDULE AND TRACKING OF RESIDENTIAL PROJECT BY EARN VALUE MANAGEMENT METHOD USING PRIMAVERA P6], August 2017 | IJIRT | Volume 4 Issue 3 | ISSN: 2349-6002.
Downloads
Published
Issue
Section
License
This work is licensed under a Creative Commons Attribution 4.0 International License.
https://creativecommons.org/licenses/by/4.0