Planning, Scheduling & Resource Allocation Analysis of a Residential Project using Primavera P6

Authors

  • Akshay Kumar Jain P.G. Scholar, Department of Civil Engineering, R.G.P.M. Bhopal, Madhya Pradesh, India Author
  • Rajesh Joshi Assistant Professor, Department of Civil Engineering, R.G.P.M. Bhopal, Madhya Pradesh, India Author

Keywords:

Primavera, Gantt Chart, Time-Cost Comparison, CPM Network, Tracking, Project Scheduling

Abstract

In this study, I am comparing a working project with a previously completed project of same aspect, for this research work we have chosen Residencial project, Bhopal. Which is on the verge of execution. For planning, scheduling and resource allocation we are using project management tool Primavera P6 8.3. From the study, it is found, how the project is planned, the sequence of work and linking relationships between activities for the whole project. In conclusion it is understood that, it is important to realize that there will be changes to the schedule logic as well as differences between the planned progress and actual progress. Based on the differences the schedule needs to be changed so as to complete the project smoothly.              

Downloads

Download data is not yet available.

References

Piyush Pramod Bagade and Prof. Abhijit Bhirud, “Review on construction project management software primavera p6” international journal of engineering sciences & research technology, ISSN: 2277-9655, January, 2018, PN (110-117).

Poonam Raykar and Ghadge A.N., “Analyzing the Critical Factors Influencing the Time Overrun and Cost Overrun in Construction Project” International Journal of Engineering Research, Volume No.5, ISSN:2319-6890, 9 Jan 2016, PN (21-25).

A. Ray Chaudhuri, B. Sivakonda Reddy and S.K. nimbal, “Resource Management in Construction Projects – a case study” Engineering Science and Technology: An International Journal (ESTIJ), ISSN: 2250-3498, Vol.2, No. 4, August 2017 PN (660 – 665)

A.R. Nikumbh and S.S. Pimpliker, “Planning and controlling of a National Highway Project- A case study”, Journal of the Indian Road Congress Paper No.613, April – June 2014 PN (91 – 102).

P M Wale1 , N D. Jain , N R Godhani , S R Beniwal and A A Mir, «Planning and Scheduling of Project using Microsoft Project (Case Study of a building in India», IOSR Journal of Mechanical and Civil Engineering, ISSN: 2320-334X, Volume 12, Issue 3 Ver. III (May. - Jun. 2015), PN 57-63.

Shaik Mohammad, Kunal B. Badgujar, B.A.Konnur and Amarsinh B. Landage “A Review of EVM Analysis with Primavera”; International Journal of Engineering Research ISSN:2319 6890(online),2347-5013 Volume No.5, Issue Special 1 9 Jan 2014 PN: 164-167

Hamid, R. Gupta, Parag S. Mahatme and Taran C. Bhagat “The cost controlling and monitoring of Construction project through earned Value management system” International Journal of Advanced Technology in Engineering and Science www.ijates.com Volume No 03, Special Issue No. 01, March 2013 ISSN (online): 2348 – 7550

P.Dayakar and M.Udhayakumar, «Study on Project Management of an Ongoing Construction project Using MSP Sub Structure” Volume2 Issue 5 Number2–Oct 2012, PN 202-212.

Stephenson, P. and Fapohunda, J.A. “Optimal Construction Resources Utilization: Reflections of Site Managers’ Attributes. The Pacific Journal of Science and Technology, Vol. 11. No. 2. November 2010 (Fall) PN 105-109.

Tranner, D. S. Stephan Jabasingh and J. Jayalakshmi “Analysis of Cost Controlling In Construction Industries by Earned Value Method Using Primavera”; Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 6( Version 1), June 2009, PN.145-153.

Prabhakar, G. P. What is Project Success: A Literature Review. International Journal of Business and Management. September, 2008.

Kerzner, H. . Project Management: A Systems Approach to Planning, and Controlling. New Dehli. CBS Publishers and Distributors Pvt. Ltd. 2003.

Downloads

Published

01-07-2019

Issue

Section

Research Articles

How to Cite

Jain, A. K., & Joshi, R. (2019). Planning, Scheduling & Resource Allocation Analysis of a Residential Project using Primavera P6 . International Journal of Scientific Research in Civil Engineering, 3(4), 01-08. https://ijsrce.com/index.php/home/article/view/IJSRCE193401