Scheduling and Monitoring of Water Supply Project at Jabalpur Using Management Tool Primavera

Authors

  • Arun Dubey P.G. Scholar, Department of Civil Engineering, S.I.R.T.E. Bhopal, Madhya Pradesh, India Author
  • Deepak Bandewar Assistant Professor, Department of Civil Engineering, S.I.R.T.E. Bhopal, Madhya Pradesh, India Author
  • Rakesh Patel Professor and H.O.D., Department of Civil Engineering, S.I.R.T.E. Bhopal, Madhya Pradesh, India Author

Keywords:

Primavera, Gantt Chart, Time-Cost Comparison, Cpm Network, Tracking, Project Scheduling

Abstract

Implementation of construction project needs a proper planning and scheduling is of vital importance for the project to be executed and run smoothly. A best schedule has to be prepared in such a way that meets the primary objectives of the total project. Those primary objectives are to create a quality project, completed on time, within budget, and in a safe work environment.
Hence in this study an ongoing construction project is taken and the execution of the project is compared with the schedule with the help of Primavera P6. An ongoing water supply project in is selected and the activities pertaining to the preconstruction, substructure and superstructure is considered for comparison. From the study, it is found, how the project is planned, the sequence of work and linking relationships between activities for the whole project.
This research is based on secondary as well as primary data. This investigation highlighted scheduling of PAYLI MULTI VILLAGE RURAL WATER SUPPLY SCHEME, DISTT. JABALPUR, NARSINGHPUR AND SEONI" for ultimate capacity of bringing 71 mld treated water (23 hours of pumping) from the backwater of Bargi Dam on river Narmada to 638 villages of Jabalpur, Narsinghpur and Seoni districts in Single Package.
              

Downloads

Download data is not yet available.

References

Kavita Dehalwar and Dr. Jagdish Singh, [Challenges And Strategies For The Improvement Of Water Management In Bhopal], European Scientific Journal January 2016 edition vol.12, No.2 ISSN: 1857 – 7881 (Print) e - ISSN 1857- 7431.

Akhil Gupta and Dr. Sanjay Tiwari, [Resource Allocation with Primavera-P6 Software], International Journal for Research in Applied Science & Engineering Technology (IJRASET) ISSN: 2321-9653, Volume 8 Issue X Oct 2020.

Shivanjali Giram, Rashmi Sabale, Abhishek Bhad and Vijay Wani, [ASSESSMENT OF RESOURCE MANAGEMENT BY USING PRIMAVERA SOFTWARE], Open Access International Journal of Science and Engineering, Volume 6 Issue 7 July 2021.

Sudarshan. S and Geena George, [COMPARISON OF PROJECT PLANNING & SCHEDULING SOFTWARE PRIMAVERA AND MICROSOFT PROJECT USED IN THE CONSTRUCTION INDUSTRY], International Journal of Engineering Technologies and Management Research, September 2021 8(9), 78-87.

Kottamasu L. N. Panakala Rao and K. Shyam Chamberlin, [Resources Optimization in Construction of a Residential Apartment by using Primavera: a Case Study], International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-7, Issue-6C2, April 2019.

Roma Silawat and Rajendra Chauhan, [ANALYSIS OF WATER QUALITY OF RIVER KALIYASOT BHOPAL, (M.P.) INDIA.], Journal of Science and Technological Researches (JSTR), Vol. 3 Issue No.1, January-March 2021.

Divya V S and C Gayathri, [Flexible Scheduling in Construction Industry by Using Primavera], International Journal for Modern Trends in Science and Technology ISSN: 2455-3778, Volume: 06, Issue No: 04, April 2020.

Satinder Chopra and Arvind Dewangan, [Developing an Efficient Schedule in Primavera P6: Significance of Activity ID & Descriptions], International Journal of Innovative Research in Science, Engineering and Technology, Vol. 3, Issue 7, July 2014.

Divya.D.S and Sahaya Nisha.J, [Flexible Scheduling in Construction Industry by Using Primavera and Histogram], International Journal of Innovative Research in Science, Engineering and Technology, Vol. 8, Issue 3, March 2019.

Hassan ElFiky, Aly Owida and Noha M. Galal, [Resource Constrained Multi-Project Scheduling Using Priority Rules: Application in the Deep-Water Construction Industry], Proceedings of the International Conference on Industrial Engineering and Operations Management Dubai, UAE, March 10-12, 2020.

Patil C B and Arun Kumar C J, [Planning, Scheduling, and Optimization of Labor Resources in the construction of Residential Apartment using Primavera P6 software], International Research Journal of Engineering and Technology (IRJET), Volume: 06 Issue: 07 | July 2019.

Archana Sen, Namita Sen and Vineesha Singh, [Issues and Challenges of Water Supply System in Bhopal City, Madhya Pradesh], Bulletin of Pure and Applied Sciences. Geology (Geological Science), Vol.41F, No.1, January-June 2022: P.129-141.

Shanghong Zhang, Jiasheng Yang, Zhongyu Wan and Yujun Yi, [Multi-Water Source Joint Scheduling Model Using a Refined Water Supply Network: Case Study of Tianjin], Water 2018, 10, 1580.

Aman Gaur, Shashank Chourey, Deepa Madathil and A. N. Brijesh Nair, [QUALITY ANALYSIS OF DRINKING WATER IN BHOPAL CITY], IJRET: International Journal of Research in Engineering and Technology, Volume: 03 Issue: 10 | Oct-2014.

Hylton Olivieria, Olli Seppänena and Ariovaldo Denis Granjab, [Improving workflow and resource usage in construction schedules through location-based management system (LBMS)], Construction Management and Economics, 2018 VOL. 36, NO. 2, 109–124.

Downloads

Published

18-05-2023

Issue

Section

Research Articles

How to Cite

Dubey, A., Bandewar, D., & Patel, R. (2023). Scheduling and Monitoring of Water Supply Project at Jabalpur Using Management Tool Primavera . International Journal of Scientific Research in Civil Engineering, 7(3), 55-70. https://ijsrce.com/index.php/home/article/view/IJSRCE237310