A Statistical Method to Evaluate the Significant Factors That Causes Schedule Delays in Indian Construction Industry

Authors

  • Gend Lal Chakrawarti Department of Civil Engineering, Babu Lal Tarabai Institute of Research & Technology, Sagar, Madhya Pradesh, India Author
  • Ravindra Kumar Raj Department of Civil Engineering, Babu Lal Tarabai Institute of Research & Technology, Sagar, Madhya Pradesh, India Author

Keywords:

Community participation, Walking Speed, Stroke Walking

Abstract

Objective : The timed up and go (TUG) test is method used to determine the functional mobility of persons with stroke. Its reliability, validity, reaction rate, fall prediction, and psychological characteristics concerning ambulation ability have been validated. However, the relationship between TUG performance and community ambulation ability is unclear. The purpose of this study was to investigate whether the TUG performance time could indicate community ambulation levels differentially in persons with chronic stroke. Design: Cross sectional study. Material and methods: Total 27 subjects (both male and female) who were previously diagnosed by a neurologist as suffering with chronic stroke were included as per inclusion and exclusion criteria and informed consent was obtained from all the subjects after the procedure was explained to them. All the subjects were assigned to one group only. Subjects were recruited from different hospitals, physiotherapy centres and communities in and around Allahabad and Dehradun. Result: The data was analyzed for 27 participants and  the mean age was 58.70 ± 6.75 years and mean of duration of stroke was 26.48 ± 12.73 months. our study showed highly significant correlation between four square step test and timed up & go test (r = .983,p<0.05) in chronic stroke patient.
Conclusions: The FSST is easy to perform and provide a quantitative measure of the ability to quickly change direction while lifting the feet off the ground. The FSST assess the ability to change direction quickly and it takes minimum space and time to administer the test. Hence, the Four Square Step Test is better test to measure dynamic balance in ambulatory chronic stroke patients
              

Downloads

Download data is not yet available.

References

https://mospi.gov.in/documents/213904/1885585/Printed+Annual+Report+202122+%28Eng.%29.pdf

Aibinu A, J. G. (2002). The effects of construction delays on project delivery in Nigerian construction industry. Int J Project Manage Pergamon. , 20(8):593–599.

Akogbe R.K.T.M., F. X. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE J Civil Eng. , 1213–1222.

Alavifar A.H., a. M. (Jan 7–9; 2014). Identification, evaluation and classification of time delay risks of construction project in Iran. Engineering and Operations Management (pp. 919–929). Bali, Indonesia: IEOM.

Al-Emad N., R. I. (2017). Ranking of delay factors for Makkah’s construction industry. MATEC Web of Conferences 103; Les Ulis (p. 03001.). France: EDP Sciences.

Alinaitwe H., A. R. (2013). Investigation into the causes of delays and cost overruns in Uganda’s public sector construction projects. J Constr Dev Countries , 18(2):33–47.

Arif F., L. S. (2015). Factors influencing accuracy of construction project cost estimates in Pakistan: perception and reality. . Int J Constr Manage. , 15(1):59–70.

Aziz R.F., A.-H. A. (2016.). Exploring delay causes of road construction projects in Egypt. Alex Eng J. , 55(2):1515–1539.

Bagaya O., S. J. (2016). Empirical study of factors influencing schedule delays of public construction projects in Burkina Faso. . J Manage Eng. , 32(5):05016014.

Bagozzi R.P., Y. Y. (1991). Assessing construct validity in organizational research. Admin Sci Quarter. , 36:421–458.

Bajjou M.S., a. C. (2018). Empirical study of schedule delay in Moroccan construction projects. International Journal of Construction Management , 2331-2327.

Black S.A., a. P. (1996.). Identification of the critical factors of TQM. . Dec Sci. , 27(1):1–21.

Chen G.X., S. M. (2017). Int J Constr Manage. Investigating the causes of delay in grain bin construction projects: The case of China. , 720-729.

Doloi H., S. A. (2012). Analysing factors affecting delays in Indian construction projects. Int J Proj Manage. , 30(4):479–489.

Durdyev S., S. S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Eng. , 134:1–12.

Enshassi A., A.-N. J. (2009). Delays and cost overruns in the construction projects in the Gaza Strip. J Financial Manage Prop Constr. , 14(2): 126–151.

Fallahnejad M.H. (2013). Delay causes in Iran gas pipeline projects. Int J Proj Manage. , 31(1):136–146.

Faridi A.S., E.-S. S. (2006). Significant factors causing delay in the UAE construction industry. Constr Manage Econ. , 24(11):1167–1176.

Frimpong Y., O. J. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. Int J Project Manage. , 21(5):321–326.

Hamzah N., K. M. (2011). Cause of construction delay - theoretical framework. . Proc Eng Elsevier. , 20:490–495.

Kazaz A., U. S. (2012 ). Causes of delays in construction projects in Turkey. . J Civil Eng Manage. , 18(3):426–435.

Khalafizadeh H., M. R. (2014). Investigating causes of delay in construction projects and presenting a solution (Case study of northwest projects of Iran). New York Sci J. , 7:43–47.

Khanh H.D., a. K. (2014). Evaluating impact of waste factors on project performance cost in Vietnam. . KSCE J Civil Eng. , 18(7):1923–1933.

Khoshgoftar M., B. A. (2010). Causes of delays in Iranian construction projects. Int J Constr Manage. , 10(2):53–69.

Kikwasi G. (2013). Causes and effects of delays and disruptions in construction projects in Tanzania. Ajceb-Conerence Series , 1(2):52.

Kottegoda N.T., a. R. (1997). Statistics, probability, and reliability for civil and environmental engineers. New York: Inc; The McGraw-Hill Companies .

Koushki P.A., A.-R. K. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. . Constr Manage Econ. , 23(3):285–294.

Kraiem Z.M., D. J. (1987). Concurrent delays in construction projects. J Construct Eng Manage. , 113(4) :591–602.

Lo T.Y., F. I. (2006.). Construction delays in Hong Kong civil engineering projects. J Constr Eng Manage. , 132(6): 636–649.

Mahamid I. (2013.). Common risks affecting time overrun in road construction projects in Palestine: Contractors’ perspective. Austr J Constr Econ Build. , 13(2):45–53.

Mahamid I., B. A. (2012 ). Causes of delay in road constructiontion projects. J Manage Eng. , 28(3):300–310.

Maqsoom A., K. M. (2018). Factors influencing the construction time and cost overrun in projects: empirical evidence from Pakistani construction industry. . Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate (pp. 769-778). Singapore: Springer.

Marzouk M.M., E.-R. T. (2014). Analyzing delay causes in Egyptian construction projects. J Adv Res. , 5(1):49–55.

Mpofu B., E. G. ( 2017.). Profiling causative factors leading to construction project delays in the United Arab Emirates. . Eng Constr Architect Manage. , 24(2):346–376.

Muya M., K. C. (2013). Cost escalation, schedule overruns and quality shortfalls on construction projects: the case of Zambia. Int J Constr Manage. , 13(1):53–68.

Odeh A.M., B. H. (2002). Causes of construction delay: traditional contracts. Int J Proj Manage. , 20: 67–73.

Patil V.M., U. A. (2017). Analysis of causes of delay in any construction project. Int J Modern Trends Eng Res. , 4(2):128–134.

Pourrostam T., a. I. ( 2011. ). Significant factors causing and effects of delay in Iranian construction projects. Australian J Basic Appl Sci. , 5:450–456.

Rachid Z., T. B. (2018). Causes of schedule delays in construction projects in Algeria. Int J Constr Manage. , 1.

Sambasivan M., D. T. (2017). Analysis of delays in Tanzanian construction industry: ransaction cost economics (TCE) and structural equation modeling (SEM) approach. Eng Constr Architect Manage , 24(2):308–325.

Sambasivan M., S. Y. (2007). Causes and effects of delays in Malaysian construction industry. . Int J Proj Manage. , 25(5):517–526.

Santoso D.S., S. S. (2016). Analyzing delays of road construction projects in Cambodia: Causes and effects. J Manage Eng. , 32(6): 05016020.

Sinesilassie E.G., T. S. (2018 ). Critical factors affecting cost performance: a case of Ethiopian construction projects. Int J Constr Manage. , 18(2):108–119.

Sun M., a. M. (2009). Taxonomy for change causes and effects in construction projects. Int J Proj Manage. , 27(6): 560–572.

Toor S.U.R., a. O. (2008). Problems causing delays in major construction projects in Thailand. . Constr Manage Econ. , 26(4):395–408.

Trauner T.J. (2009.). Construction delays: understanding them clearly, analyzing them correctly. Oxford, United Kingdom : Butterworth-Heinemann.

Tumi S.A.H., O. A. (2009, November). Causes of delay in construction industry in Libya. . International Conference on Economics and Administration., (pp.265–272).

Downloads

Published

29-01-2023

Issue

Section

Research Articles

How to Cite

Chakrawarti, G. L., & Raj, R. K. (2023). A Statistical Method to Evaluate the Significant Factors That Causes Schedule Delays in Indian Construction Industry . International Journal of Scientific Research in Civil Engineering, 7(1), 72-87. https://ijsrce.com/index.php/home/article/view/IJSRCE22716

Similar Articles

1-10 of 15

You may also start an advanced similarity search for this article.