Scheduling And Monitoring of a Case Study of a Commercial Complex (Bansal One) Using Primavera P6
Keywords:
Primaver, Scheduling, Management, Planning, Activity, Delay, RiskAbstract
Project management is a skill development technique which says that project can be laid on an easy ongoing way to protect the losses and damages occur at site. This technique is very effective in managing big projects where proper management at site is mandatorily required.
Construction project manages the projects considering all boundary conditions such as equipment’s, resources, skilled persons, labor, machinery etc. These tools helps in promoting project speed and management of all these equipments lead to a successful project completion in a bounded time duration.
In this paper presenting case study scheduling and monitoring using management tool primavera p6
Downloads
References
Piyush Pramod Bagade andProf. Abhijit Bhirud, “Review on construction design operation software primavera p6” transnational journal of engineering lores & exploration technology, ISSN 2277-9655, January, 2018, PN( 110- 117).
Poonam Raykar and GhadgeA.N., “ assaying the Critical Factors impacting the Time Overrun and Cost Overrun in Construction Project ” International Journal of Engineering Research, VolumeNo. 5, ISSN2319- 6890, 9 Jan 2016, PN( 21- 25).
A. Ray Chaudhuri,B. Sivakonda Reddy andS.K. nimbal, “ Resource Management in Construction systems – a case study ” Engineering Science and Technology An International Journal( ESTIJ), ISSN 2250- 3498,Vol. 2,No. 4, August 2017 PN( 660 – 665)
A.R. Nikumbh andS.S. Pimpliker, “ Planning and controlling of a National Highway Project- A case study ”, Journal of the Indian Road Congress PaperNo. 613, April – June 2014 PN( 91 – 102).
P M Wale1, ND. Jain, N R Godhani, S R Beniwal and A A Mir,« Planning and Scheduling of Project using Microsoft Project( Case Study of a structure in India», IOSR Journal of Mechanical and Civil Engineering, ISSN 2320-334X, Volume 12, Issue 3 Ver. III( May. -Jun. 2015), PN 57- 63.
Shaik Mohammad, KunalB. Badgujar,B.A.Konnur and AmarsinhB. Landage “A Review of EVM Analysis with Primavera ”; International Journal of Engineering Research ISSN23196890( online),2347- 5013 VolumeNo. 5, Issue Special 1 9 Jan 2014 PN 164- 167
Hamid,R. Gupta, ParagS. Mahatme and TaranC. Bhagat “The cost controlling and covering of Construction design through earned Value operation system ” International Journal of Advanced Technology in Engineering and Sciencewww.ijates.com Volume No 03, Special IssueNo. 01, March 2013 ISSN( online) 2348 – 7550
P.Dayakar andM.Udhayakumar,« Study on Project Management of an Ongoing Construction design Using MSP Sub Structure ” Volume2 Issue 5 Number2 – Oct 2012, PN 202- 212.
Stephenson,P. and Fapohunda,J.A. “ Optimal Construction coffers Application Reflections of point directors ’ Attributes. The Pacific Journal of Science and Technology,Vol. 11.No. 2. November 2010( Fall) PN 105- 109.
Tranner,D.S. Stephan Jabasingh andJ. Jayalakshmi “ Analysis of Cost Controlling In Construction diligence by Earned Value Method Using Primavera ”; Int. Journal of Engineering Research and Applicationswww.ijera.com ISSN 2248- 9622,Vol. 4, Issue 6( Version 1), June 2009,PN.145- 153.
Prabhakar,G.P. What's Project Success A Literature Review. International Journal of Business and Management. September, 2008.
Kerzner,H.. Project Management A Systems Approach to Planning, and Controlling. New Dehli. CBS Publishers and DistributorsPvt.Ltd. 2003.
Cinch,M. and Li,H., 2003. Resource- exertion Critical- Path system for Construction Planning. Journal Of Construction Engineering and Management © ASCE/ July/ August 2003. ISSN 3365, PN 13- 19. Piyush Pramod Bagade andProf. Abhijit Bhirud, “ Review on construction design operation software primavera p6 ” transnational journal of engineering lores & exploration technology, ISSN 2277- 9655, January, 2018, PN( 110- 117).
Poonam Raykar and GhadgeA.N., “ assaying the Critical Factors impacting the Time Overrun and Cost Overrun in Construction Project ” International Journal of Engineering Research, VolumeNo. 5, ISSN2319- 6890, 9 Jan 2016, PN( 21- 25).
A. Ray Chaudhuri,B. Sivakonda Reddy andS.K. nimbal, “ Resource Management in Construction systems – a case study ” Engineering Science and Technology An International Journal( ESTIJ), ISSN 2250- 3498,Vol. 2,No. 4, August 2017 PN( 660 – 665)
A.R. Nikumbh andS.S. Pimpliker, “ Planning and controlling of a National Highway Project- A case study ”, Journal of the Indian Road Congress PaperNo. 613, April – June 2014 PN( 91 – 102).
P M Wale1, ND. Jain, N R Godhani, S R Beniwal and A A Mir,« Planning and Scheduling of Project using Microsoft Project( Case Study of a structure in India», IOSR Journal of Mechanical and Civil Engineering, ISSN 2320-334X, Volume 12, Issue 3 Ver. III( May. -Jun. 2015), PN 57- 63.
Shaik Mohammad, KunalB. Badgujar,B.A.Konnur and AmarsinhB. Landage “A Review of EVM Analysis with Primavera ”; International Journal of Engineering Research ISSN23196890( online),2347- 5013 VolumeNo. 5, Issue Special 1 9 Jan 2014 PN 164- 167
Hamid,R. Gupta, ParagS. Mahatme and TaranC. Bhagat “The cost controlling and covering of Construction design through earned Value operation system ” International Journal of Advanced Technology in Engineering and Sciencewww.ijates.com Volume No 03, Special IssueNo. 01, March 2013 ISSN( online) 2348 – 7550
P.Dayakar andM.Udhayakumar,« Study on Project Management of an Ongoing Construction design Using MSP Sub Structure ” Volume2 Issue 5 Number2 – Oct 2012, PN 202- 212.
Stephenson,P. and Fapohunda,J.A. “ Optimal Construction coffers Application Reflections of point directors ’ Attributes. The Pacific Journal of Science and Technology,Vol. 11.No. 2. November 2010( Fall) PN 105- 109.
Tranner,D.S. Stephan Jabasingh andJ. Jayalakshmi “ Analysis of Cost Controlling In Construction diligence by Earned Value Method Using Primavera ”; Int. Journal of Engineering Research and Applicationswww.ijera.com ISSN 2248- 9622,Vol. 4, Issue 6( Version 1), June 2009,PN.145- 153.
Prabhakar,G.P. What's Project Success A Literature Review. International Journal of Business and Management. September, 2008.
Kerzner,H.. Project Management A Systems Approach to Planning, and Controlling. New Dehli. CBS Publishers and DistributorsPvt.Ltd. 2003.
Cinch,M. and Li,H., 2003. Resource- exertion Critical- Path system for Construction Planning. Journal Of Construction Engineering and Management © ASCE/ July/ August 2003. ISSN 3365, PN 13- 19.
Downloads
Published
Issue
Section
License
This work is licensed under a Creative Commons Attribution 4.0 International License.
https://creativecommons.org/licenses/by/4.0