Planning and Scheduling of a Suspension Cable Bridge Using Project Management Tool Primavera P6

Authors(2) :-Ankit Jain, K. K. Punjabi

Attributable to an augmenting context of environment, Construction industry is ever upfront for the development and advancement in tools and equipment features, tools of communication, techniques of efficient management, educating the human resources about it. This unique specialization necessitates highly focused whose construction was planned to start at Bhopal, Madhya Pradesh, India. Project Planning and Controlling tools or techniques. In the current study, implementation of the computer based Project Management software/tool Primavera P6 for the Planning, Scheduling and Allocation of resources for a Suspension Cable Arch Bridge It helps to know the resemblance between the planned the planned progress of construction work and actual progress of the performed work. Thus the essentiality and the advantages of using Primavera will be outlined through the data results obtained. The acceptance of the software Primavera as a platform of scheduling is been on a boom in Multi National Construction Companies, but due to ignorance and lack of Project Management concepts and discourage towards the use of computer based programs, small and medium scale Indian construction companies confront various issues such as inefficient planning, project delays, inefficiency of resources and many other issues. Therefore, attempt to educate one such medium scale construction company about the advantages of Primavera in execution of any construction projects efficiently.

Authors and Affiliations

Ankit Jain
P. G. Scholar, Department of Civil Engineering, SATI Vidisha, Madhya Pradesh, India
K. K. Punjabi
Professor, Department of Civil Engineering, SATI Vidisha, Madhya Pradesh, India

Planning, Scheduling, Resources Allocation, Primavera P6, Resource Levelling.

  1. Prof. A. Beam Chaudhuri, B. Sivakonda Reddy, "Asset Management in Construction Projects - a contextual analysis" Engineering Science and Technology: An International Journal (ESTIJ), ISSN: 2250-3498, Vol.2, No. 4, August 2012 PN (660 - 665)
  2. Indrasen Singh, P. Venkateswaralu, "Arranging and controlling of a National Highway Project-A contextual analysis", Journal of the Indian Road Congress Paper No.613, April - June 2014 PN (91 - 102)
  3. Antony Prasanath MA, Thirumalai Raja K, "Investigation of expense and calendar Performance of Residential Building Projects by EVM system", Journal of Construction Engineering, Technology and Management ISSN: 2347-7253, Vol. 4, (2014) PN (1-7)
  4. Tarek Hegazy, Wail Menesi, "Basic Path Segments Scheduling Technique" Journal of Construction Engineering and Management ASCE/(Oct 2010) PN (1078-1085)
  5. Awad Hanna, Aviad Shapira, Mounir Asmar and Craig Taylor, "Effect of group planning on task execution", Practice Periodical on Structural Design and Construction ASCE (2013) PN (35 - 44)
  6. Robert B. Harris, "Pressing strategy for Resource Leveling", Journal of Construction Engineering and Management © ASCE, vol no 116, June 1990 PN (331 - 350)
  7. Khaled El-Rayes and Dho Heon - "Advancing Resource Leveling in Construction Projects", Journal of Construction Engineering and Management © ASCE, Vol. 135, No. 11, November 1, 2009. PN (1172 - 1180)
  8. James E. Seibert and Gerald W. Evans, "TimeConstrained Resource Leveling", Journal of Construction Engineering and Management, ASCE Vol. 117, No. 3, September, 1991. PN (503 - 520)
  9. O. Shaked and A. Warszawski, "Conshed : Expert System for Scheduling of Modular Construction Projects", Journal of Construction Engineering and Management, ASCE/vol 118, Sept. 1992 PN (488 - 506)
  10. Piotr Jaskowski and Anna Sobotka, "Booking Construction Projects Using Evolutionary Algorithm", Journal of Construction Engineering and Management, ASCE/Aug 2006 PN (861 - 870)
  11. Daniel Castro-Lacouture, Gürsel A. Süer Julian Gonzalez-Joaqui; and J. K. Yates, " Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method" ASCE , ISSN 0733-9364/2009/10-PN (1096- 1104)
  12. A. Kastor a, K. Sirakoulis, "The viability of asset leveling apparatuses for Resource Constraint Project Scheduling Problem", Science Direct International Journal of Project Management 27 (2009) PN 493- 500
  13. Liberatore MJ, Pollack-Johnson B, Smith CA. Undertaking n development: programming use and research heading. J Constr Eng Manage 2001;127(2):101- 7.
  14. IS : 7272 ( Part I ) - 974 "Suggestion For Labor Output Constants For Building Work Part I North Zone ( Sixth Reprint February 2001 )
  15. Maharashtra Jeevan Pradhikaran ( Government of Maharashtra Undertaking ) Schedule Of Rates For The Year 2012 - 2013 ( Effective from 24th December 2012 )
  16. “Estimating, Costing, Specification and Valuation in Civil ENGG.

Publication Details

Published in : Volume 4 | Issue 1 | January-February 2020
Date of Publication : 2020-01-30
License:  This work is licensed under a Creative Commons Attribution 4.0 International License.
Page(s) : 25-33
Manuscript Number : IJSRCE20415
Publisher : Technoscience Academy

ISSN : 2456-6667

Cite This Article :

Ankit Jain, K. K. Punjabi, "Planning and Scheduling of a Suspension Cable Bridge Using Project Management Tool Primavera P6", International Journal of Scientific Research in Civil Engineering (IJSRCE), ISSN : 2456-6667, Volume 4, Issue 1, pp.25-33, January-February.2020
URL : https://ijsrce.com/IJSRCE20415

Article Preview

Contact Us

  • Address : 3 & 4, Sterling Plaza, Indira Circle, 150 Feet Ring Road, Rajkot-360005, Gujarat, India